Question

Table 7.4

Activity Predecessor Time(weeks)
A -- 8
B A 6
C -- 4
D C 9
E A 11
F B 3
G D, E, F 1

Using Table 7.4, what is the slack associated with activity B?

A) 1 week

B) 2 weeks

C) 3 weeks

D) None of these is the correct activity slack for B.

Answer