Question

Table 7.4

Activity Predecessor Time(weeks)
A -- 8
B A 6
C -- 4
D C 9
E A 11
F B 3
G D, E, F 1

Using Table 7.4, what is the minimum number of activities that would have to be crashed to cause a decrease in the project's earliest completion date?

A) one activity

B) two activities

C) three activities

D) four or more activities