Question

Table 7.4

Activity Predecessor Time(weeks)
A -- 8
B A 6
C -- 4
D C 9
E A 11
F B 3
G D, E, F 1

Using Table 7.4, what is the latest finish time for activity C?

A) week 4

B) week 6

C) week 8

D) week 10