Question

Table 7.4

Activity Predecessor Time(weeks)
A -- 8
B A 6
C -- 4
D C 9
E A 11
F B 3
G D, E, F 1

Using Table 7.4, what is the largest amount of slack that any activity in the project has?

A) zero weeks

B) two weeks

C) four weeks

D) six weeks

Answer

This answer is hidden. It contains 58 characters.