Question

Table 7.4

Activity Predecessor Time(weeks)
A -- 8
B A 6
C -- 4
D C 9
E A 11
F B 3
G D, E, F 1

Using Table 7.4, what is the earliest completion time for this project?

A) 18 weeks

B) 19 weeks

C) 20 weeks

D) 21 weeks