Question

Table 7.5

Activity Predecessor Time (days)
A -- 8
B -- 6
C -- 3
D A,B 10
E C 8
F A 5
G D,E 3
H G 4

Using Table 7.5, what is the latest start time for activity E?

A) day 8

B) day 10

C) day 12

D) day 14