Question

Table 7.5

Activity Predecessor Time (days)
A -- 8
B -- 6
C -- 3
D A,B 10
E C 8
F A 5
G D,E 3
H G 4

Using Table 7.5, what is the earliest that activity D can be finished?

A) 18 days

B) 8 days

C) 13 days

D) 25 days

Answer