Question

Table 7.5

Activity Predecessor Time (days)
A -- 8
B -- 6
C -- 3
D A,B 10
E C 8
F A 5
G D,E 3
H G 4

Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time?

A) 0 days

B) 2 days

C) 5 days

D) 7 days

Answer

This answer is hidden. It contains 58 characters.