Question

Table 7.5

Activity Predecessor Time (days)
A -- 8
B -- 6
C -- 3
D A,B 10
E C 8
F A 5
G D,E 3
H G 4

Using Table 7.5, every day the construction crew is on-site costs $1000. What activities would you consider crashing to reduce the project completion cost?

A) Activity E

B) Activity F

C) Activity G

D) All of these activities would be candidates for crashing.

Answer

This answer is hidden. It contains 58 characters.