Question

Table 7.5

Activity Predecessor Time (days)
A -- 8
B -- 6
C -- 3
D A,B 10
E C 8
F A 5
G D,E 3
H G 4

Disaster strikes and activity F takes 20 days instead of the anticipated 5 days. Using Table 7.5, how much longer will the project last than initially estimated?

A) 15 days

B) 0 days

C) 7 days

D) 3 days