Table 7.8

Activity Predecessor Normal Time (days) Crashing Time (days) Crashing Cost/day
A -- 5 1 $200
B -- 7 1 $500
C -- 5 1 $200
D A 10 2 $300
E B 6 1 $400
F A, C 7 2 $650
G B 4 1 $500
H E, D, G 6 1 $350

Using Table 7.8, what is the earliest possible completion time for activity E after crashing?

A) day 11

B) day 13

C) day 15

D) day 17