Question

Table 7.8

Activity Predecessor Normal Time (days) Crashing Time (days) Crashing Cost/day
A -- 5 1 $200
B -- 7 1 $500
C -- 5 1 $200
D A 10 2 $300
E B 6 1 $400
F A, C 7 2 $650
G B 4 1 $500
H E, D, G 6 1

$350

Using Table 7.8, what is the latest start time for activity E?

A) day 7

B) day 8

C) day 9

D) day 10

Answer

This answer is hidden. It contains 58 characters.