Selected accounts with some amounts omitted are as follows:

Work in Process
Aug. 1 Balance275,000 Aug. 31 Goods finished1,030,000
31 Direct materialsX
31 Direct labor 450,000
31 Factory overheadX
Factory Overhead
Aug. 1–31 Costs incurred145,000Aug. 1 Balance15,000
31 AppliedX

If the balance of Work in Process on August 31 is $220,000, what was the amount debited to Work in Process for factory overhead in August, assuming a factory overhead rate of 30% of direct labor costs?

a. $10,000

b. $70,000

c. $120,000

d. $135,000

Answer

This answer is hidden. It contains 1 characters.