Question

Select which of the following does not describe how the sequence of activities can be drawn to reflect the availability of a limited quantity of resources.
a. The activities using the limited resources are shown in a ladder relationship as they are available.
b. The activities using the limited resources are shown in a loop relationship as they are available.
c. The activities requiring the limited resource are assigned at different times.
d. If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources.

Answer

This answer is hidden. It contains 1 characters.