Question

Schedule control involves four steps. Place these steps in their proper order by stating the letter sequence of their proper order.
A. Analyzing the schedule to determine which areas may need corrective action
B. Recalculating the schedule to evaluate the effects of the planned corrective actions
C. Revising the plan to incorporate the chosen corrective actions
D. Deciding what specific corrective actions should be taken
a. A,B,C,D
b. A,D,C,B
c. D,A,C,B
d. D,A,B,C

Answer

This answer is hidden. It contains 1 characters.