Scenario 9.11

Demand = 50,000 units/week

Standard deviation of weekly demand = 15,000 units

Average lead time = 8 weeks

Standard deviation of lead time: 3 weeks

Cycle-service level = 80%

A continuous review system is used to control inventory.

Use the information in Scenario 9.11. If the firm decides to increase its cycle-service level to 90%, what is the new reorder point if all other parameters remain the same for this product?

A) greater than 550,000 units

B) greater than 400,000 units but less than or equal to 550,000 units

C) greater than 250,000 units but less than or equal to 400,000 units

D) greater than 150,000 units but less than or equal to 250,000 units

E) greater than 0 but less than or equal to 150,000 units