Sanchez Company's output for the current period was assigned a $400,000 standard direct labor cost. The direct labor variances included a $10,000 unfavorable direct labor rate variance and a $4,000 favorable direct labor efficiency variance. What is the actual total direct labor cost for the current period?

A. $414,000.

B. $386,000.

C. $394,000.

D. $406,000.