Ray Contractors have agreed to build Yen's house for $25,000 in two years. However, six months after the work began, Ray Contractors demand an additional $5,000 from Yen to complete the work. Yen agrees, but when the work was completed, Yen pays Ray Contractors only $20,000. Ray decides to sue Yen. Analyze the case.