Positive slack indicates the maximum amount of time
a. that the activities on the critical path should be accelerated to complete the project by the required completion time.
b. that each of the activities in the project can be delayed without jeopardizing completion of the project by the required completion time.
c. that the activities with the positive slack should be accelerated to complete the project by the required completion time.
d. that the activities on a particular path can be delayed without jeopardizing completion of the project by the required completion time.