Question

Output from the Gantt chart drawn for a machining process is shown below. Determine the makespan of the process.
Job Waiting Time (hr) Delivery Time (hr)
1 0 10
2 10 15
3 1 16

A. 10 hours
B. 15 hours
C. 13.667 hours
D. 16 hours