Question

Midwest Rocks receives and produces an order. What is the companys cycle efficiency assuming the following times were measured during production of this order?

Process time: .7 days Inspection time: .25 days Move time: 1.05 days Wait time: .5 days

A. 10%

B. 28%

C. 42%

D. 20%

E. 50%

Answer

This answer is hidden. It contains 28 characters.