Max has contracted with Lew to have his house painted. The contract specifically stated that the job was to be completed by 8/25. Lew completes the job on 8/26. Max has suffered no loss due to the delay. The job was otherwise done exactly to all contract requirements and specifications. If Max sues Lew for breach of contract due to the missed completion date, were the courts to award damages, what type of damages would most likely be awarded?
A.punitive damages
B.consequential damages
C.restitution
D.nominal damages