Question

Latest start time (LS) is the latest time by which a specific activity must be
a. started in order for the entire project to be finished by its required completion time.
b. started in order for the entire project to be started by its required completion time.
c. finished in order for the entire project to be finished by its required completion time.
d. finished in order for the entire project to be started by its required completion time.