Question

Latest finish time (LF) is the latest time by which a specific activity must be
a. started in order for the entire project to be finished by its required completion time.
b. completed in order for the entire project to be finished by its required completion time.
c. started in order for the entire project to be started by its required completion time.
d. completed in order for the entire project to be started by its required completion time.

Answer

This answer is hidden. It contains 1 characters.