Keith assembles peanut valves and the recorded data is displayed in the table. What is the select time for this job element?


Time (minutes) Observations
2.5 15
3.0 23
3.5 27

A) greater than or equal to 3 minutes

B) less than 3 minutes but greater than or equal to 2.7 minutes

C) less than 2.7 minutes but greater than or equal to 2.4 minutes

D) less than 2.4 minutes

Answer

This answer is hidden. It contains 64 characters.