Question


Job Process Time Due Date Days Since Arrival
A 5 7 11
B 9 5 9
C 7 9 9
D 2 3 7
E 3 4 5
F 8 8 2

Use the information in the preceding table and sequence the six jobs using first come, first served (FCFS) and earliest due date (EDD). Calculate the average flow time and average past due. It is now time zero.

Answer

This answer is hidden. It contains 161 characters.