Question


Job Days Since Arrival Process Time Due Date
Hepner 0 7 1
Cheng 4 2 3
Allison 1 8 10
Miller 2 8 10
Dickson 4 12 11
Noel 5 16 2
Bahouth 4 16 3

Use the information in the preceding table and sequence the seven jobs using first come, first served (FCFS) and earliest due date (EDD). Calculate the average flow time and average past due. It is now time 5.