Question

In , the project manager is responsible for the project results, while the functional managers are responsible for providing the resources needed to achieve the results.
a. an autonomous project organizational structure
b. a functional organizational structure
c. a matrix organizational structure
d. a project management office

Answer

This answer is hidden. It contains 1 characters.