Question

In , the project manager does not have complete authority over the project team, because administratively the members still work for their respective functional managers.
a. an autonomous project organizational structure
b. a functional organizational structure
c. a matrix organizational structure
d. a project management office

Answer

This answer is hidden. It contains 1 characters.