Question

In order to establish a basis from which to calculate a schedule using the estimated durations for the activities, it is necessary to
a. say who has responsibility for the first task.
b. enter the tasks into a project management information system.
c. select an estimated start time and a required completion time for the overall project.
d. edit the calendars for the resources in the project management information system.