Question

In aggregate planning,
A.the concern is over a long-range planning horizon.
B.output levels are set in the face of certain demand.
C."aggregate" implies that planning is done for a single overall measure of output or at most a few products.
D.firms should never consider overtime, hiring, firing, or subcontracting.