In addition to showing the technical constraints among activities, how does the network logic also take into account resource constraints?
a. Activities that use the same resource may not be able to occur in parallel to each other.
b. Activities that use different resources may be shown in a serial relationship.
c. The activities could be shown in a loop relationship.
d. Resources that are unlimited are not shown in a resource assignment.

Answer

This answer is hidden. It contains 1 characters.