In a network diagram, an activity:

A) is the largest unit of work effort consuming both time and resources that a project manager can schedule and control.

B) is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control.

C) should always be something the company has had experience with.

D) must always have a single, precise estimate for the time duration.