Question

If the NPV (Net Present Value) of a project with one sign reversal is positive, then the project's IRR (Internal Rate of Return) ________ the required rate of return.
A) must be less than
B) must be greater than
C) could be greater or less than
D) The project's IRR cannot be determined without actual cash flows.

Answer

This answer is hidden. It contains 1 characters.