Question

If each unit of Kyotos product takes two hours to produce and the labor rate is expected to be $10 per hour, what is the budgeted labor cost for May?
A. $4,000
B. $4,240
C. $5,360

D. $5,600
E. $5,840

Answer

This answer is hidden. It contains 130 characters.