Question

Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question. What is the least number of resources that can be assigned to the project if all five tasks occur in parallel?
a. 24 workers
b. 1.5 workers per day
c. 7 workers
d. 2 workers