Question

Given the following information pertaining to item AX143, determine the appropriate number of kanban cards that should be used to support production.
Demand rate = 500 units/week

Time for container to complete circuit = 2 weeks
Safety stock = 30 percent
Size of container = 5 units
A. <100 units
B. Between 100 and 500 units
C. >500 units
D. There is not enough information to answer the question

Answer

This answer is hidden. It contains 1 characters.