Given the following information:


Job Workcenter/ Machine Hours
1 A/3, B/3, C/4
2 B/3, A/1, C/2
3 C/2, B/3, A/3

Lead time for completion of a job is a function of:
A. Capacity and demand
B. Capacity and priority decisions
C. Capacity and supply decisions
D. None of the above