Question

Given the following information:


Job Workcenter/ Machine Hours
1 A/3, B/3, C/4
2 B/3, A/1, C/2
3 C/2, B/3, A/3

Use a Gantt chart to schedule the jobs in order 1, 2, 3 and assume that jobs cannot be split. What is the makespan?
A.12
B.9
C.14
D.3

Answer

This answer is hidden. It contains 107 characters.