Question

Garman observes a worker assembling peanut valves and records the data displayed in the table. During one of the cycles, the worker knocked the shaft out of the fixture and had to realign the fixtures. What is the select time for this job element?


Time (seconds) Observations
20 15
25 12
30 12
240 1

A) less than 23 seconds

B) greater than or equal to 23 seconds but less than 26 seconds

C) greater than or equal to 26 seconds but less than 29 seconds

D) greater than or equal to 29 seconds

Answer

This answer is hidden. It contains 64 characters.