Question

Gantt charts can be used to:

A) monitor the progress of jobs but cannot be used to sequence work on each machine.

B) sequence work on each machine but cannot be used to monitor the progress of each job.

C) monitor the progress of jobs and sequence work on each machine.

D) monitor the average number of defective parts generated by a machine on each job.

Answer

This answer is hidden. It contains 54 characters.