Fun Vehicles, Inc. makes beach buggies on an assembly line. The total productive time to make one buggy is 300 seconds. The current line has a 90-second cycle time and consists of four workstations. The balance delay of this line must be:

A) 0%.

B) greater than 0% but less than 6%.

C) greater than 6% but less than 12%.

D) greater than 12% but less than 18%.

Answer

This answer is hidden. It contains 83 characters.