Free slack is the amount of time a specific activity can be
a. postponed without delaying the earliest start time of its immediately preceding activities.
b. postponed without delaying the earliest start time of its immediately succeeding activities.
c. accelerated without delaying the latest start time of its immediately succeeding activities.
d. accelerated without delaying the latest finish time of its immediately preceding activities.