Question

Fletcher Company collected the following data regarding production of one of its products. Compute the fixed overhead cost variance.

Direct labor standard (2 hrs. @ $12.75/hr.) $25.50 per finished unit

Actual direct labor hours 81,500 hrs.

Budgeted units 42,000 units

Actual finished units produced 40,000 units

Standard variable OH rate (2 hrs. @ $14.30/hr.) $28.60 per finished unit

Standard fixed OH rate ($336,000/42,000 units) $8.00 per unit

Actual cost of variable overhead costs incurred $1,140,000

Actual cost of fixed overhead costs incurred $338,000

A. $18,300 favorable.

B. $18,000 favorable.

C. $18,000 unfavorable.

D. $18,300 unfavorable.

E. $14,300 unfavorable.

Answer

This answer is hidden. It contains 79 characters.