Question

Fletcher Company collected the following data regarding production of one of its products. Compute the direct labor efficiency variance.

Direct labor standard (2 hrs. @ $12.75/hr.) $25.50 per finished unit

Actual direct labor hours 81,500 hrs.

Actual finished units produced 40,000 units

Actual cost of direct labor $1,100,250

A. $19,125 favorable.

B. $80,250 favorable.

C. $61,125 favorable.

D. $19,125 unfavorable.

E. $80,250 unfavorable.

Answer

This answer is hidden. It contains 116 characters.