Question

Figure to accompany Table 7.7

Table 7.7

ACTIVITY NORMAL TIME CRASH TIME NORMAL COST ($000s) CRASH COST ($000s) AVAILABLE WEEKS OF CRASHING CRASHING COST / WEEK
A 4 2 8 14
B 3 2 9 11
C 4 4 10 10
D 5 3 10 15
E 4 1 11 14
F 1 1 6 6

Which activity should be crashed first for the project shown in Table 7.7?

A) A

B) B

C) C

D) D