Figure to accompany Table 7.1

Table 7.1

Activity Activity Time Earliest Start Earliest Finish Latest Start Latest Finish Slack
A 2 0 0 2 0
B 1 2 3 3 4 1
C 3 2 5 2 5 0
D 7 3 10 4 11
E 3 5 8 11 3
F 5 11 5 11 0
G 4 11 15 11 15 0

Using the information shown in Table 7.1, what is the project duration?

A) 15

B) 14

C) 12

D) 10

Answer