Question

End item A requires three component parts: B, C, and D. The BOM indicates that for each completed A, 1 unit of B, 2 units of C, and 1 unit of D are required. Current inventory for the four items is as follows: there are 15 As, 40 Bs, 50 Cs, and 15 Ds in stock. If the lead time for all items is 1 week and there are no scheduled receipts for any item, how many units of product A can be delivered to customers at the start of next week (week 2) if you realize now the BOM has just been changed? You now realize it takes 2 units of B to make 1 finished unit of A.
A. 10 units
B. 15 units
C. 20 units
D. 25 units

Answer

This answer is hidden. It contains 191 characters.