Question

Eliminating negative slack by reducing durations of activities will involve a trade-off in the form of
a. no change in costs and an increase in scope.
b. a decrease in costs and an expansion in scope.
c. an increase in costs or a reduction in scope.
d. an decrease in costs and no change in scope.