Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time.


Activity Immediate Predecessor(s) Time (Weeks)
A --- 3
B --- 4
C A 6
D B 9
E B 6
F C, D 6
G D, E 8
H G, F 9

Activity Earliest Start Earliest Finish Latest Start Latest Finish Slack
A




B




C




D




E




F




G




H